1. The behavioral responsibilities of a project manager may also include dealing with:
[A]The public
[B]Regulatory personnel
[C]The legal environment
[D]Environmental issues
[E]All of the above
2. The difference between the BCWS and the BCWP is referred to as the:
[A]Schedule variance
[B]Cost variance.
[C]Estimate of completion
[D]Actual cost of the work performed
[E]None of the above
3. "Paraphrasing" is most closely associated with which part of the communication process?
[A]encoding
[B]decoding
[C]barriers
[D]feedback
[E]None of the above.
4. A Gantt chart is useful in determining:
[A]the level of effort for a task
[B]when a task starts and stops
[C]how tasks are related to each other
[D]who is assigned to do a task
[E]All of the above.
5. A contract originated bilaterally may be developed by _____ .
[A]quotation request from suppliers
[B]proposal request
[C]bid invitation release
[D]B and C
[E]All of the above.
6. In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance review?
[A]Not working directly with the assigned functional employees
[B]Employees spend only a short amount of time assigned to the project
[C]Not being knowledgeable enough to evaluate employees on technical judgment
[D]All of the above
[E]A and B only
7. Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:
[A]Baseline costs
[B]Budgeted costs.
[C]Estimates upon completion costs
[D]Scheduled costs
[E]None of the above
8. Which of the following is not a definition to determine a product's ability to operate as intended?
[A]distance
[B]performance
[C]function
[D]condition
[E]All are definitions
9. A work breakdown structure is most useful for:
[A]identifying individual tasks for a project
[B]scheduling the start of tasks
[C]developing a cost estimate
[D]determining potential delays
[E]A and C
10. Reaching an understanding of concessions is accomplished in the _____ stage of negotiations.
[A]protocol
[B]probing
[C]scratch bargaining
[D]closure
[E]agreement
11. The primary consideration of product management is to know the _____.
[A]probability of product's performance with specified parameters
[B]ability the product has to perform its intended function
[C]ability of a product to be produced within existing parameters
[D]functionality the product will provide over its useful life
[E]All of the above
12. The reason that cost management is so difficult in project management is that:
[A]Projects by definition and nature are non-recurring events and are therefore difficult to predict.
[B]There are no tools for identifying project tasks.
[C]Project managers do not care about tracking costs, as only schedules are important to all project managers.
[D]A and B only
[E]B and C only
13. Using visual aids during management/customer presentations will:
[A]hold the interest of the audience
[B]strengthen the learning process by adding a visual dimension to the auditory dimension
[C]stay in view longer, thus bringing back listeners who may have strayed
[D]All of the above.
[E]A and B only
14. Which of the following organizational forms would be likely to have an individual with the title of Vice President for Project Management?
[A]Classical / traditional
[B]Pure project
[C]Matrix
[D]Project coordinator
[E]None of the above
15. A contract is legally binding and must comprise all but one of the following:
[A]legal capacity
[B]mutual assent
[C]approved negotiations
[D]consideration
[E]legality
Home
Multiple Choice Questions
PGCPM
PMP
Project Management
Project Management MCQ
Project Management Quiz - 32
Project Management Quiz - 32
Tags
# Multiple Choice Questions
# PGCPM
# PMP
# Project Management
# Project Management MCQ
Share This
Project Management MCQ
Subscribe to:
Post Comments (Atom)
Most Played Quizzes Last Week
-
1. There are two universities which are named in honour of Ahilya Bai. One is Devi Ahilya Vishwa Vidyalaya in Indore, Madhya Pradesh and the...
-
1. Which of the following is considered to be poor e-mail etiquette? [A]Have a proper sign off: Regards, Sincerely, etc. [B]Responding to me...
-
1. When was Lal Bahadur Shastri Born? [A]2 october 1904 [B]2 November 1904 [C]2 December 1904 [D]2 September 1904 2. Which slogan is a...
-
1. Navaratri is a festival that spans nine nights (and ten days). The word Navaratri literally means nine nights in Sanskrit, nava meaning n...
-
1. If you want to borrow a book, where will you go? Bookstore Library Museum Stationary 2. If you want to have a little fun in the water, th...
-
1. The Navratri commences with the 1st night devoted to the puja of Maa "Shailputri". "Shail" means mountains; "Par...
-
1. What is BharatGen? An initiative for AI in Indian languages A new government portal An AI-powered social media platform An educational...
-
1. Which among the following books are not written by Sister Nivedita? [A]Kali the mother [B]The Webo Of Indian Life [C]The Religio...
-
1. Which two umbrella schemes were recently approved by the Indian Union Cabinet? PM-Kisan and PM-RKVY PM-RKVY and Krishonnati Yojana Kris...
-
This time the quiz is focused on Banking Industry. Check out how familiar you are with these banks' logos. 1. Guess the logo? Hint:Estab...
No comments:
Post a Comment