GK Quiz, General Knowledge, Latest Current Affairs, Business Quiz, Management Quiz, Finance, Project Management, PMP Resources, IT Quiz, Bollywood Quiz, Finance, HR, OB, Supply Chain Management, Multiple Choice Questions, Bank PO Entrance Exam Questions, Civil Services Question Bank, Quant, Verbal, GMAT, SAT, TOEFL Resources Questions, Numerical Ability, Fun Quiz, KBC

Project Management Quiz - 35

1. The purpose of a dummy activity in an activity-on-arrow diagram is to:
[A]Identify a task that could be replaced by another.
[B]Take the slack time into account.
[C]Show a task that is not necessarily needed.
[D]Denote a milestone.
[E]Show a dependency relationship.



2. When planning, organizing, coordinating, and controlling a project an important human resources skill or ability would be
[A]Building multi-disciplinary teams
[B]Managing conflict
[C]Communicating orally and in writing with all levels of personnel
[D]Involving senior management
[E]All are important



3. Which is not a negotiation tactic?
[A]Imposing deadlines
[B]surprises
[C]person with authority is absent
[D]reasoning together
[E]all are negotiations tactics



4. Which of the following is referred to as sunk cost:
[A]management reserve
[B]contingency fund
[C]cost budgeted for construction under water
[D]expended funds over which there is no further control
[E]forecasted budget over-runs



5. A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
[A]Change the scope baseline
[B]Prepare a variance report
[C]Call a meeting of the configuration control board
[D]Change the project's objectives
[E]Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline



6. As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:
[A]Insignificant.
[B]Reduced.
[C]Unchanged.
[D]Increased.
[E]Doubled.



7. Group brainstorming encourages all of the following except:
[A]Team building
[B]Uninhibited verbalization
[C]Decision making
[D]Analysis of alternatives
[E]Convergent thinking



8. Non-conformance penalties are a form of _____.
[A]quality incentive
[B]risk sharing
[C]contract negotiations
[D]quality assurance programs
[E]None of the above.



9. Risk Event Status is defined as _____ .
[A]Risk Probability x Amount At Stake.
[B]the severity of the consequences.
[C]how likely the event is to occur with risk.
[D](Cost + Benefit + Business Risk) / Insurable Risk.
[E]B and C



10. There are hard causes of conflict (e.g. conflicting schedules) and soft causes. Soft causes are as important as hard causes. Soft causes include diversity of disciplinary expertise, _____, and the project manager's power of reward and punishment.
[A]Performance tradeoffs
[B]Ambiguity of roles
[C]Administrative procedures
[D]Determining earned value
[E]



11. Which of the following is referred to as payback period:
[A]the number of periods required to recover the initial investment
[B]the rate of return on the investment
[C]the number of periods required to bring project cost back to the original budget, based on current performance
[D]loan payment schedule
[E]None of the above



12. Which one of the following is not an acquisition method?
[A]advertising
[B]invitation
[C]negotiation
[D]purchase
[E]all are acquisition methods



13. At least _____of the cost of quality are the direct responsibility of management.
[A]0.25
[B]0.85
[C]0.5
[D]1
[E]0.33



14. Fast tracking means to:
[A]Speed up a project through parallel tasks.
[B]Swap one task for another.
[C]Reduce the number of tasks if possible.
[D]B and C.
[E]None of the above.



15. Formal written correspondence is mandated in which of the following situations:
[A]Product undergoes casual in-house testing
[B]Client requests additional work not covered under contract
[C]Project manager calls a meeting
[D]B and C only
[E]None of the above



No comments:

Most Played Quizzes Last Week