1. The priority of the Quality function is ________ priority:
[A]Equal to cost and schedule
[B]Higher than cost and schedule
[C]Lower than cost and schedule
[D]None of the above
2. A Pareto diagram helps the project manager to :
[A]Focus on the most critical issues to improve quality
[B]Focus on stimulating thinking
[C]Explore a desired future outcome
[D]Determine if a process is out of control
3. What will be shown in a Gantt chart but not in a responsibility matrix?
[A]Time
[B]Tasks
[C]Interrelationships
[D]Who is in charge of each task
4. A work package is:
[A]The lowest level of a work breakdown structure
[B]The level of the WBS where cost data are collected
[C]Made up of multiple costs accounts
[D]A and B
5. The scope baseline is the original:
[A]Project schedule and budget
[B]Description in the project charter
[C]Project Plan plus or minus approved changes
[D]Performance measure
6. In the context of projects, temporary means that:
[A]Projects have a finite time duration with definite start and end dates
[B]Every project has a definite beginning
[C]The project can be cancelled at any point of time depending upon the whims of the senior executive
[D]Projects have no significance to the permanent sustainability of a corporation
7. A work breakdown structure is most useful for:
[A]Identifying individual tasks for a project
[B]Scheduling the start of tasks
[C]Developing a cost estimate
[D]A and C
8. If a risk has a 50% chance of happening in any given month, and if the project is expected to last for 8 months, the probability that this risk event will occur during the last month of the project is:
[A]25%
[B]50%
[C]75%
[D]100%
9. In the arrow diagramming method (ADM), __________ do not consume time or resources:
[A]Events
[B]Activities
[C]Float
[D]Arrows
10. In a three time estimate using PERT, if the optimistic estimate for a task is 6 days and pessimistic estimate is 12 days, what is the most likely estimate if the mean is 7 days:
[A]7 days
[B]8 days
[C]6 days
[D]12 days
11. A negative float is present when?
[A]The late start date is earlier than the early start date
[B]The critical path supports the imposed end date
[C]The early finish date is equal to the late finish date
[D]The late start date is later than early start date
12. Task B cannot begin until 10 days after task A begins is best described as a:
[A]Finish to start relationship
[B]Start to start relationship
[C]Start to start with a 10 days lag
[D]Start to start with a 5 day lead
13. Amongst all of the following, the most important component of project control is the:
[A]Project charter
[B]Project schedule
[C]Work breakdown structure
[D]Assignment of responsibility for work
14. Which of the following is most frequently used to indicate task relationships?
[A]Bar chart
[B]Network diagram
[C]Gantt chart
[D]Work breakdown structure
15. Preliminary cost estimates are meaningful during the _______ phase of the project:
[A]Conceptual
[B]Planning
[C]Control
[D]Execution
Project Management Quiz - 58
Tags
# PGCPM
# PMP
# PMP Certification
# PMP Questions
# Project Management
Share This
Project Management
Labels:
PGCPM,
PMP,
PMP Certification,
PMP Questions,
Project Management
Subscribe to:
Post Comments (Atom)
Most Played Quizzes Last Week
-
1. What is Baisakhi? A festival of harvest A festival of flowers A festival of colors A festival of lights 2. In which month is Baisakhi ...
-
1. What is Bihu? A folk song of Assam A dance form of Assam A type of traditional food A popular festival of Assam 2. How many Bihus are...
-
1. What is the theme for Earth Day 2022? Restore Our Earth Protect Our Species Climate Action Beat Plastic Pollution 2. When is Earth Day ce...
-
1. What percentage of the Earth's surface is covered by water? 50% 60% 70% 75% 2. Which term refers to a large body of land? Island...
-
1. Where was Guru Gobind Singh Ji born? [A]Patna [B]Anandpur [C]Amritsar [D]Bhopal 2. Guru Gobind Singh Ji was the _____ sikh guru? [A...
-
1. What was the original name of Sarojini Naidu? [A]Aparna Mukhyopadhyay [B]Sarojini Bandopadhyay [C]Padmini Gangopadhyay [D]Sarojini...
-
1. Ramakrishna Paramhansa was born on ? [A]18 January 1838 [B]18 February 1836 [C]18 February 18366 [D]18 April 1839 2. Which among the f...
-
1. Which of these cricketers holds the record for playing the highest number of test matches. [A]Stephen Flaming [B]Alan Border [C]Stev...
-
1. In which century did Adi Shankaracharya live? 8th century 9th century 10th century 11th century 2. What was Adi Shankaracharya's birt...
-
1. Which city is called the Pink city? Lucknow Hyderabad Jaipur Kanpur 2. Which city is called the city of Lakes? Delhi Bengaluru Mumbai Uda...
No comments:
Post a Comment