1. When the project is considered successful?
[A]When deliverables are by & large handed over to a client
[B]When all the deliverables as per checklist are delivered
[C]When project team members are dispersed
[D]When the total payment is received by the contractor


2. What are the methods of project evaluation?
[A]Project audits
[B]Quality control
[C]Post implementation reviews
[D]A & C


3. Which of the following are included as part of a scope statement?
[A]Project justification
[B]Project deliverables
[C]Project objectives
[D]All of the above


4. Project life cycles are very useful for _____ and _____ .
[A]Configuration management, termination
[B]Objective setting, information gathering
[C]Standardization, control
[D]Configuration management, weekly status updates


5. Work packages are used to:
[A]Represent units of work at a level where work is performed.
[B]Clearly distinguish one work package from all others assigned to a single functional group.
[C]Limit the work to be performed to relatively short periods of time.
[D]All of the above.


6. "Hard logic" in the preparation of a network refers to:
[A]Discretionay dependencies
[B]External depenencies
[C]Mandatory dependencies
[D]All of the above


7. The erection of foundation formwork before the placement of foundation concrete would be an example of a _____ dependency.
[A]Discretionary
[B]Mandatory
[C]External
[D]Soft logic


8. Sources for data on activity durations and resource requirements can be gathered from which of the following:
[A]Past project records (historical data)
[B]Commercial techniques (standard practices, rules of thumb)
[C]Past project team members knowledge (experience, oldtimers)
[D]All of the above


9. Which of the following can affect network durations?
[A]Skills of the resource pool
[B]Calendar dates
[C]Constraints
[D]A and B only


10. A completion of a local government study resides on your critical path. This would most likely be referred to as:
[A]Soft logic
[B]Hard logic
[C]An external dependency
[D]A mandatory dependency


11. A project may be undertaken to address
[A]A new business need
[B]Maintain a running process
[C]Re-work
[D]Manufacture a car battery


12. The quality considerations to be followed in the project are decided:
[A]During it's execution
[B]By the quality department
[C]At the beginning of the project
[D]Depending on the project's cost


13. The development of modern project management began in:
[A]1950
[B]1960
[C]1970
[D]1975


14. What do the three sides of the conventional triangle in project management represent?
[A]Customer, time and cost
[B]Quality, customer and scope
[C]Scope, time and quality
[D]Scope, time and cost


15. Using the diagram given below, the late start (LS) of activity F is at the beginning of day:

[A]9
[B]8
[C]7
[D]14


Comments

Popular posts from this blog

Email Etiquette Quiz

1. Which of the following is considered to be poor e-mail etiquette? [A]Have a proper sign off: Regards, Sincerely, etc. [B]Responding to messages as soon as possible [C]Using different colors/fonts/formatting to emphasize certain words [D]Keeping the message personal 2. What should be the tone of a professional email message? [A]Formal [B]Casual [C]Formal with slight usage of slangs [D]Conversational 3. What is the purpose of the BCc field? [A]To send copies of business e-mail to coworkers without the knowledge of boss [B]To respect contact's privacy [C]To keep e-mail looking clean [D]To send copies to anyone you want 4. What is the best way to send a very large attachment? [A]Compress the file (zip it up) [B]Send it first thing in the morning so that person can look into it with fresh mind [C]Send it only during weekend when traffic is low [D]Compress the file, then ask first when would be the best time to e-mail it 5. What is Flame? [A]A post or email message that exhibi

Krishna Janmashtami Quiz

1. Krishna Janmashtami is an annual Hindu festival that celebrates the birth of Krishna, the ____________ avatar of Vishnu. [A]Sixth [B]Seventh [C]Eighth [D]Ninth 2. Krishna was the son of? [A]Devaki [B]Vasudeva [C]Kansa [D]A & B 3. Janmashtami is an important festival particularly to which tradition of Hinduism? [A]Shaivism [B]Shaktism [C]Smartism [D]Vaishnavism 4. Which festival is celebrated every August/September, the day after Krishna Janmashtami mainly in Maharashtra? [A]Makhan Handi [B]Dahi Handi [C]Ghee Handi [D]Mitti Handi 5. In which city Bhagwan Krishna was born? [A]Dwarka [B]Vrindavan [C]Mathura [D]Kurukshetra 6. Janmashtami or Sri Krishna Jayanti celebrates the birthday of Krishna. It is also known by which name in Maharashtra and South India? [A]Gokulashtami [B]Bal Ashtami [C]Krishna Ashtami [D]Nandashtami 7. Fiji's Janmastami celebrations last for eight days, leading up to the eighth day, the day Krishna was born. Janmastami in Fiji is known as [A]G

Class 2 | Means of Communication | EVS General Awareness | Quiz

1. We keep in touch with everyone through- means of communication means of transport means of production none 2. Which of the following are personal means of communication? Letter Mobile e-mail All of the above 3. We post our letters in a - Wooden Box Almirah Letter box Bank 4. From where do we get postal stamps? Bank Post office Milk booth Grocery shop 5. Which of the following are means of mass communication? Radio Newspaper Telephone Radio and Newspaper 6. Which of the following is NOT a means of personal communication? Radio Letter Post card Fax 7. Which means of communication will you use to call your friend for your birthday party? Newspaper Television Mobile Letter 8. Urgent messages were earlier sent by telegram. The message in a telegram had to be ___________ as each word was paid for. Long Short No message is sent by telegram Very long 9. Which of the following are also called modern means of communication? Telephone Mobile e-mail All of the above 10. Which of the following i