1. The bottom-up estimates generally have an accuracy of: 
[A]-25% to +75% 
[B]-25% to +30% 
[C]-5% to +10% 
[D]+15% to -15% 
 
2. What are the three most common cost estimating techniques? 
[A]Top-down, parametric and bottom-up 
[B]Analogous, top down and bottom-up 
[C]Parametric, bottom-up and detailed 
[D]Monte Carlo, bottom-up and parametric  
 
3. Cost baseline can: 
[A]Change during the project life cycle 
[B]Be affected by scope change 
[C]Be affected by change in time schedule 
[D]All of the above 
 
4. Cost baseline is: 
[A]Another name for cost estimates 
[B]Given by upper management 
[C]Time phased budget of project that is used to measure project's cost performance 
[D]Provided in the contract to the customers
 
5. Zero defects, Continuous quality improvement and TQM: 
[A]Advocate a proactive way to improve quality 
[B]Rely on the workers to implement better quality 
[C]Means that there are zero defects 
[D]All of the above 
 
6. A company wants to introduce a defect free environment. The authority and capability to introduce this: 
[A]Lies with the project manager 
[B]Lies with the management 
[C]Lies with the functional manager 
[D]Lies equally with - the project manager, the functional manager and management
 
7. A critical path is shown in a: 
[A]WBS 
[B]Bar chart 
[C]Project network diagram 
[D]Resource histogram 
 
8. The critical path in a project network is the path that: 
[A]Is the longest path in a network 
[B]Is decided by a project manager 
[C]Allows some flexibility in scheduling a start time 
[D]Should be executed when other activities on a non critical paths have been finished
 
9. Which of the following impacts the critical path? 
[A]Executing a forward pass 
[B]Reduce the free float of an activity 
[C]Executing a backward pass 
[D]Changing the task duration of a critical path activity
 
10. The series of interconnected activities, which determine the duration of the project is known as: 
[A]The critical path 
[B]The free float plan 
[C]The critical work plan 
[D]The management plan
 
11. Project X has a total budget of $9 million and was to be completed in 8 months. While reviewing the progress of the project at the end of 3 months, the following data was presented: BCWS or PV = $3 Million; BCWP or EV = $2.5 Million and ACWP or AC = $3 Million. What is Estimate at Completion if the efficiency of capital deployed will change to 100% from now onwards: 
[A]$9 Million 
[B]$8.5 Million 
[C]$9.5 Million 
[D]$10.8 Million 
 
12. Project X has a total budget of $9 million and was to be completed in 8 months. While reviewing the progress of the project at the end of 3 months, the following data was presented: BCWS or PV = $3 Million; BCWP or EV = $2.5 Million and ACWP or AC = $3 Million. What is Estimate at Completion if the efficiency of capital deployed remains the same?  
[A]$3.6 Million 
[B]$10.8 Million 
[C]$7.5 Million 
[D]$12 Million 
 
13. Continuous Improvement Process or CIP is a quality concept that states: 
[A]What is satisfactory today may become unsatisfactory tomorrow 
[B]Does not advocate any great leap forward 
[C]Management should keep looking for ways to improve and change processes 
[D]All of the above 
 
14. Zero defects states that: 
[A]There are zero errors in a process 
[B]There is no tolerance for any defects within the system 
[C]See how to improve processes in order to avoid all defects 
[D]B and C 
 
15. The modern trend in quality is to: 
[A]Focus more on customer satisfaction and conformance to requirements 
[B]Give the customer more than what he wants 
[C]Give the customer less than what he wants 
[D]Rely on worker to maintain quality 
 
Home
PGCPM
PMP
PMP Certification
PMP Questions
Project Management
Project Management MCQ
Project Management Quiz - 72
Project Management Quiz - 72
Tags
# PGCPM
# PMP
# PMP Certification
# PMP Questions
# Project Management
# Project Management MCQ
      
Share This 
Project Management MCQ
Subscribe to:
Post Comments (Atom)
Most Played Quizzes Last Week
- 
1. What was the old name of Varanasi(Banaras)? [A]Patliputra [B]Magadh [C]Indraprastha [D]Kashi 2. On which river bank Varanasi is situated...
- 
1. What percentage of the Earth's surface is covered by water? 50% 60% 70% 75% 2. Which term refers to a large body of land? Island...
- 
1. If you want to borrow a book, where will you go? Bookstore Library Museum Stationary 2. If you want to have a little fun in the water, th...
- 
1. Which of the following is considered to be poor e-mail etiquette? [A]Have a proper sign off: Regards, Sincerely, etc. [B]Responding to me...
- 
1. Which among the following books are not written by Sister Nivedita? [A]Kali the mother [B]The Webo Of Indian Life [C]The Religio...
- 
1. When was Baba Banda Singh Bahadur born? 1670 1680 1690 1700 2. What was the original name of Baba Banda Singh Bahadur? Guru Gobind ...
- 
1. Identify the logo? Hint:American multinational banking and financial services corporation headquartered in Charlotte, North Carolina ...
- 
Business World B-School Competitions Business Management Introduction to Management Ethics / Governance Business Ethics and...
- 
1. Guru Nanak Gurpurab marks the birth anniversary of the Guru Nanak Dev Ji. It is one of the most sacred festival of which religion? [A]Hin...
- 
1. What is the original name of Bangalore in Kannada language? [A]Begur [B]Bangaru [C]Bengaluru [D]None of the above 2. Once called a pens...
 
 
 
 
 
 
No comments:
Post a Comment