Skip to main content

PMP Certification Sample Paper(Project Management Quiz - 70)

1. For a network using PERT for determining activity durations, one of the activities in this network is having a standard deviation of 10 minutes. This activity has pessimistic time duration of 75 minutes. Calculate the optimistic time duration of this activity.
[A]65 minutes
[B]85 minutes
[C]135 minutes
[D]15 minutes



2. An activity has an Optimistic duration of 100 days, a Pessimistic duration of 158 days and a Most likely duration of 120 days. The time estimate which would be considered for this activity is:
[A]120 days
[B]123 days
[C]100 days
[D]160 days



3. 3 time estimates using PERT methodology is generally based on:
[A]Modified normal distribution
[B]Alpha distribution
[C]Triangular distribution
[D]None of the above



4. 3 time estimates should be used when the level of uncertainties is:
[A]Low
[B]Manageable as we have done similar work before
[C]High
[D]Very low



5. The work effort for an activity is:
[A]The work units needed to complete an activity
[B]The work period available to perform the work of the project
[C]The calendar days taken to complete an activity
[D]The work units needed to complete an activity plus the weekends



6. My work time is 8 hours a day from Monday - Friday. The duration for completing activity A is 192 hours. I have 4 persons who are available full time to complete the activity. If I begin performing A on Monday what is the elapsed time for A to finish?
[A]6 workdays
[B]9 days
[C]8 days
[D]12 workdays



7. In a three time estimate using PERT, if the optimistic estimate for a task is 10 days, most likely is 15 days and pessimistic is 20 days what is the standard deviation of the task?
[A]1.67 days
[B]2 days
[C]1.37 days
[D]Insufficient information to determine the value



8. A dependency that requires that the initial design be completed before detailed design can start is an example of:
[A]Discretionary Dependency
[B]Mandatory dependency
[C]External dependency
[D]Internal dependency



9. The ______________ task relationship is the most common task scheduling relationship:
[A]Start to start
[B]Finish to start
[C]Finish to finish
[D]Start to finish



10. The preceding activity must start before the succeeding activity can finish denotes which kind of dependency?
[A]Finish to start
[B]Start to start
[C]Finish to Finish
[D]Start to finish



11. When a task cannot be completed before another task is completed, it is called a?
[A]Critical relationship
[B]Finish to finish dependency
[C]Concurrent task
[D]Finish to start dependency



12. Lag means:
[A]Amount of time a task can be delayed without delaying the project
[B]Amount of time a task can be delayed without delaying the early start date of its successor activity/activities
[C]A modification of the logical relationship in a network which delays a successor activity
[D]The amount of time a project is lagging behind from the original schedule



13. In creating your network diagram, you know that the second task cannot be started till 4 days have passed after the completion of first task due to external reasons. Another name for this compulsory wait is:
[A]Free float
[B]Float
[C]Lead
[D]Lag



14. Which term describes a modification of a logical relationship that accelerates a successor task?
[A]Lead
[B]Leveling
[C]Crashing
[D]Lag



15. A lag can occur _______:
[A]In a finish to start relationship
[B]In a finish to finish relationship
[C]In a start to start relationship
[D]All of the above



Comments

Popular posts from this blog

Email Etiquette Quiz

1. Which of the following is considered to be poor e-mail etiquette? [A]Have a proper sign off: Regards, Sincerely, etc. [B]Responding to messages as soon as possible [C]Using different colors/fonts/formatting to emphasize certain words [D]Keeping the message personal 2. What should be the tone of a professional email message? [A]Formal [B]Casual [C]Formal with slight usage of slangs [D]Conversational 3. What is the purpose of the BCc field? [A]To send copies of business e-mail to coworkers without the knowledge of boss [B]To respect contact's privacy [C]To keep e-mail looking clean [D]To send copies to anyone you want 4. What is the best way to send a very large attachment? [A]Compress the file (zip it up) [B]Send it first thing in the morning so that person can look into it with fresh mind [C]Send it only during weekend when traffic is low [D]Compress the file, then ask first when would be the best time to e-mail it 5. What is Flame? [A]A post or email message that exhibi

Krishna Janmashtami Quiz

1. Krishna Janmashtami is an annual Hindu festival that celebrates the birth of Krishna, the ____________ avatar of Vishnu. [A]Sixth [B]Seventh [C]Eighth [D]Ninth 2. Krishna was the son of? [A]Devaki [B]Vasudeva [C]Kansa [D]A & B 3. Janmashtami is an important festival particularly to which tradition of Hinduism? [A]Shaivism [B]Shaktism [C]Smartism [D]Vaishnavism 4. Which festival is celebrated every August/September, the day after Krishna Janmashtami mainly in Maharashtra? [A]Makhan Handi [B]Dahi Handi [C]Ghee Handi [D]Mitti Handi 5. In which city Bhagwan Krishna was born? [A]Dwarka [B]Vrindavan [C]Mathura [D]Kurukshetra 6. Janmashtami or Sri Krishna Jayanti celebrates the birthday of Krishna. It is also known by which name in Maharashtra and South India? [A]Gokulashtami [B]Bal Ashtami [C]Krishna Ashtami [D]Nandashtami 7. Fiji's Janmastami celebrations last for eight days, leading up to the eighth day, the day Krishna was born. Janmastami in Fiji is known as [A]G

Class 2 | Means of Communication | EVS General Awareness | Quiz

1. We keep in touch with everyone through- means of communication means of transport means of production none 2. Which of the following are personal means of communication? Letter Mobile e-mail All of the above 3. We post our letters in a - Wooden Box Almirah Letter box Bank 4. From where do we get postal stamps? Bank Post office Milk booth Grocery shop 5. Which of the following are means of mass communication? Radio Newspaper Telephone Radio and Newspaper 6. Which of the following is NOT a means of personal communication? Radio Letter Post card Fax 7. Which means of communication will you use to call your friend for your birthday party? Newspaper Television Mobile Letter 8. Urgent messages were earlier sent by telegram. The message in a telegram had to be ___________ as each word was paid for. Long Short No message is sent by telegram Very long 9. Which of the following are also called modern means of communication? Telephone Mobile e-mail All of the above 10. Which of the following i